The Minister of Power, Mr Joseph Tegbe, says the new Abeokuta Transmission Substation will be inaugurated in March 2027.
Tegbe gave the assurance on Friday in Abeokuta after inspecting the ongoing project, expressing satisfaction with the progress of work.
He said most of the equipment had been installed, while the remaining components were awaiting installation and testing.
According to him, the facility is expected to undergo cold commissioning in December, followed by hot commissioning and energisation ahead of its full inauguration in March 2027.
The minister said the Abeokuta facility was one of five substations being developed under the first batch of the transmission expansion programme.
Others are located in Ayede, Oyo State; Sokoto; Offa, Kwara State; and Onitsha, Anambra State.
He said the five projects would collectively add 986 megawatts to Nigeria’s transmission capacity.
Tegbe explained that the projects were part of the Federal Government’s efforts to strengthen electricity transmission and improve reliable power supply across the country.
He stressed that increasing electricity generation without corresponding improvements in transmission and distribution infrastructure would continue to limit power supply.
The minister disclosed plans to meet with four electricity distribution companies, including Abuja, Ikeja, Eko and Ibadan, to address challenges affecting electricity delivery.
He said the government was adopting a coordinated approach involving gas suppliers, generating companies, the Nigerian National Petroleum Company Ltd. and relevant ministries to tackle challenges across the electricity value chain.
On the Federal Government’s $1 trillion economy ambition, Tegbe described reliable electricity supply as essential to industrialisation and economic growth.
He said Nigeria was targeting 10,000 megawatts of electricity generation by 2031 and transmission capacity of at least 19,000 megawatts.
According to him, achieving the targets would improve electricity supply to commercial and industrial consumers and support the country’s economic ambitions.
Also speaking, the Managing Director of FGN Power Company, Mr Kenny Anuwe, said the Abeokuta substation upgrade would inject an additional 480 megawatts into Ogun State’s industrial corridor.
Anuwe explained that the first batch of Phase One of the Presidential Power Initiative (PPI) was upgrading the existing 132/33kV facility into a modern 330/132/33kV substation within 18 months.
He said the upgraded facility would improve power evacuation, strengthen network reliability and meet growing electricity demand from industries, businesses and residential consumers.
According to him, the initiative is designed to address longstanding infrastructure challenges across Nigeria’s electricity generation, transmission and distribution networks.
Anuwe said the PPI pilot phase, implemented in partnership with Siemens Energy, delivered 10 power transformers and 10 mobile substations, adding about 1,080 megawatts of wheeling capacity nationwide.
He reaffirmed the company’s commitment to coordinating stakeholders and ensuring the initiative delivers measurable improvements in electricity supply.